Fall seasonal buoy tending operations summary for sector Great Lakes
Date of last update: March 05, 2026 9:43 loc
Beauharnois Lock to Sarnia
| Beauharnois Lock to Sarnia |
Planned Date
(Real Date) |
|---|---|
| PR-01 - Beauharnois Canal - Seaway (completed at 100%) | from Dec 18 to 28, 2025 (from Dec 25 to 26, 2025) |
| PR-02 - Lake St Francis - Seaway (completed at 84%) | from Dec 18 to 28, 2025 (Started Nov 25, 2025) |
| PR-03 - Lake St Francis (Small Commercial/Recreational) (completed at 100%) | from Nov 08 to 14, 2025 (from Nov 06 to 07, 2025) |
| PR-04 - Lake St Lawrence - Seaway (completed at 100%) | from Dec 18 to 28, 2025 (Dec 28, 2025) |
| PR-05 - Lake St Lawrence (Small Commercial / Recreational) (completed at 100%) | from Nov 08 to 14, 2025 (Nov 09, 2025) |
| PR-06 - St Lawrence River - Seaway (completed at 100%) | from Dec 18 to 28, 2025 (from Nov 20 to Dec 31, 2025) |
| PR-07 - Prescott to Kingston (completed at 100%) | from Nov 20 to 23, 2025 (Nov 15, 2025) |
| PR-08 - Canadian Middle Channel/ Bateau Channel (completed at 100%) | from Nov 23 to 27, 2025 (from Nov 15 to 17, 2025) |
| PR-09 - Kingston to Toronto (completed at 100%) | from Nov 22 to 23, 2025 (from Nov 23 to 25, 2025) |
| PR-10 - Bay of Quinte (Small Commercial / Recreational) (completed at 100%) | from Nov 15 to 18, 2025 (from Nov 13 to 14, 2025) |
| PR-11 - Lake Ontario U.S Buoys (completed at 89%) | from Nov 01 to 07, 2025 (Started Nov 27, 2025) |
| PR-13 - Welland Canal - Seaway (completed at 100%) | Dec 31, 2025 (from Jan 08 to 15, 2026) |
| PR-15 - Western Lake Erie - Commercial (completed at 100%) | from Dec 15 to 16, 2025 (Dec 14, 2025) |
| PR-16a - Lake Erie (Small Commercial/Recreational) (completed at 100%) | from Nov 06 to 10, 2025 (Nov 22, 2025) |
| PR-16b - Lake Erie (Small Commercial/Recreational) (completed at 100%) | from Dec 01 to 04, 2025 (Dec 01, 2025) |
| PR-17a - Detroit River - Commercial (completed at 100%) | from Dec 05 to 06, 2025 (from Dec 08 to 11, 2025) |
| PR-17b - Detroit River - Commercial (completed at 100%) | from Dec 09 to 10, 2025 (from Dec 15 to 16, 2025) |
| PR-17c - Detroit River - Commercial (completed at 100%) | from Dec 21 to 22, 2025 (Dec 15, 2025) |
| PR-19 - Detroit River - Peche Island (completed at 100%) | from Nov 17 to 18, 2025 (Nov 11, 2025) |
| PR-20 - Lake St.Clair (completed at 100%) | from Nov 11 to 16, 2025 (from Nov 08 to 14, 2025) |
| PR-21a - St. Clair River (Small Commercial / Recreational) (completed at 100%) | from Nov 20 to 30, 2025 (Dec 07, 2025) |
| PR-21b - St. Clair River Commercial (completed at 100%) | from Dec 24 to 26, 2025 (from Dec 16 to 22, 2025) |
| PR-22 - Ottawa River (Britannia Section) (completed at 100%) | from Oct 27 to Nov 04, 2025 (Nov 05, 2025) |
| PR-27 - Ottawa River - Pembroke Secton (completed at 100%) | from Oct 27 to Nov 04, 2025 (Nov 07, 2025) |
Sarnia to Thunder Bay
| Sarnia to Thunder Bay |
Planned Date
(Real Date) |
|---|---|
| PS-01 - Lake Huron - Commercial (completed at 100%) | from Nov 20 to 26, 2025 (from Nov 19 to Jan 16, 2025) |
| PS-01b - Lake Huron - Goderich (completed at 100%) | from Nov 21 to 30, 2025 (Nov 23, 2025) |
| PS-02 - Parry Sound Channel - Commercial (completed at 100%) | from Dec 09 to 11, 2025 (from Dec 07 to 11, 2025) |
| PS-02a - Parry Sound Channel - Inner Harbour (completed at 100%) | from Dec 01 to 02, 2025 (Nov 25, 2025) |
| PS-03 - Southern Georgian Bay - Commercial (completed at 100%) | from Nov 20 to 26, 2025 (from Nov 22 to 24, 2025) |
| PS-04 - Meaford Firing Range - CYD 501 (completed at 100%) | from Nov 20 to 26, 2025 (Nov 23, 2025) |
| PS-05 - Midland Channel (completed at 100%) | from Nov 24 to 30, 2025 (from Nov 20 to 21, 2025) |
| PS-06 - Byng Inlet (completed at 100%) | from Nov 16 to 19, 2025 (Nov 10, 2025) |
| PS-07 - Northern Georgian Bay (completed at 100%) | from Nov 12 to 15, 2025 (from Nov 10 to 11, 2025) |
| PS-08a - North Channel (completed at 100%) | from Nov 06 to 11, 2025 (from Nov 12 to 13, 2025) |
| PS-08b - North Channel (completed at 100%) | from Nov 15 to 20, 2025 (from Nov 10 to 13, 2025) |
| PS-08c - North Channel (completed at 100%) | from Nov 15 to 20, 2025 (Nov 10, 2025) |
| PS-09a - St. Mary's River (completed at 100%) | from Nov 15 to 18, 2025 (Nov 10, 2025) |
| PS-09b - St. Mary's River (completed at 100%) | from Dec 10 to 20, 2025 (Nov 21, 2025) |
| PS-11 - Thunder Bay (completed at 100%) | from Nov 20 to 23, 2025 (Nov 23, 2025) |
| PS-13 - Georgian Bay Small Craft - Port Severn to Parry Sound (completed at 100%) | from Nov 24 to 30, 2025 (Nov 21, 2025) |
| PS-14 - Georgian Bay Small Craft - Parry Sound to Byng (completed at 100%) | from Nov 20 to 23, 2025 (Nov 20, 2025) |
| PS-16 - Lake of Bays (completed at 100%) | from Nov 01 to 04, 2025 (Nov 02, 2025) |
| PS-17 - Lake Muskoka (completed at 100%) | from Nov 01 to 04, 2025 (Nov 02, 2025) |
| PS-18 - Lake Rosseau (completed at 100%) | from Nov 01 to 04, 2025 (Nov 02, 2025) |
| PS-19 - Lake Joseph (completed at 100%) | from Nov 01 to 04, 2025 (Nov 02, 2025) |
| PS-20 - Lake Nipissing (completed at 100%) | from Nov 06 to 11, 2025 (from Nov 08 to 15, 2025) |
| PS-21 - Lake of the Woods (completed at 100%) | from Oct 01 to 21, 2025 (from Oct 19 to 28, 2025) |
Weather Buoy
| Weather Buoy |
Planned Date
(Real Date) |
|---|---|
| EC-01 - Lake Ontario Prince Edward Point "45135" Weather Buoy (completed at 100%) | from Nov 15 to 18, 2025 (Nov 10, 2025) |
| EC-02 - Lake Ontario U.S. NOAA "45012" Weather Buoy (completed at 100%) | from Nov 01 to 07, 2025 (Nov 10, 2025) |
| EC-03 - Lake Ontario West (Ajax) "45159" Weather Buoy (completed at 100%) | from Nov 15 to 18, 2025 (Nov 08, 2025) |
| EC-05 - Lake Ontario Grimsby "45139" Weather Buoy (completed at 100%) | from Nov 15 to 18, 2025 (Dec 05, 2025) |
| EC-06 - Lake Erie "Port Colborne 45142" Weather Buoy (completed at 100%) | from Nov 20 to 23, 2025 (Dec 02, 2025) |
| EC-07 - Lake Erie "Port Stanley "45132" Weather Buoy (completed at 100%) | from Nov 20 to 23, 2025 (Nov 23, 2025) |
| EC-08 - Lake St. Clair "ODAS 45147" Weather Buoy (completed at 100%) | from Nov 11 to 16, 2025 (Dec 01, 2025) |
| EC-09 - Lake Huron "ODAS 45149" Weather Buoy (completed at 100%) | from Nov 20 to 26, 2025 (Nov 18, 2025) |
| EC-10 - Georgian Bay South "ODAS 45143" Weather Buoy (completed at 100%) | from Nov 27 to 30, 2025 (Nov 25, 2025) |
| EC-11 - Georgian Bay North "ODAS 45137" Weather Buoy (completed at 100%) | from Nov 27 to 30, 2025 (Nov 24, 2025) |
| EC-12 - North Channel "ODAS 45154" Weather Buoy (completed at 100%) | from Nov 15 to 18, 2025 (Nov 11, 2025) |
| EC-13 - Lake Superior "Slate Islands ODAS 45136" Weather Buoy (completed at 100%) | from Nov 13 to 18, 2025 (Nov 15, 2025) |
| EC-14 - Lake Nipissing"ODAS 45152" Weather Buoy (completed at 100%) | from Nov 06 to 11, 2025 (Nov 15, 2025) |
| EC-15 - Lake of the Woods "ODAS 45148" Weather Buoy (completed at 100%) | from Oct 01 to N/A (Oct 19, 2025) |